Last update August 2014
Project Budget: $8,777,959
Project Description: This project includes the rehabilitation and modernization of buildings (A, C, D, E), and portables (G, H, I, J, K, L, M, N, O, P, Q, R, S & T).
Work includes (but not limited to):
- Major student restrooms ADA upgrades at buildings C, D, & E
- Modernization & upgrades at buildings A, C, D & E
- New fire alarm systems
- Seismic retrofit at buildings C, D, & E
- Interior & exterior painting at all buildings surfaces & trims
- Replacement of sink cabinets & plumbing fixtures to meet ADA code
- Refurbishing of classroom caseworks
- Replacement of flooring, tackable walls
- T-bar ceiling replacement affected by seismic retrofit work
- Window blinds at all classrooms
- Threshold replacement and other architectural finish upgrades
- Replacement of existing sewer line system